What is the timeline?

November 13, 2023 Go-Live

Common HR System project timeline shows Nov 2023 go-live

  • Configuration Build (Pass 4A) - Feb 14 to April 28, 2023
    • Security role analysis and configuration; system setup 
  • Campus Testing (Pass 5B) - June 1 to July 28, 2023
    • Project Team members system test in a non-production database
  • Final System Validation (Pass 6C) - Sept 5 to Oct 20, 2023
  • Go-Live/Move to Production - November 2023

What is the difference between CHRS and CHRS Recruiting?

describing the difference between CHRS and CHRS Recruiting