Our university, in partnership with the Chancellor’s Office CHRS Project Management Team are part of the first four campuses, Fullerton, Cal Maritime, and Stanislaus to go live on the new CHRS system.

What is the timeline?

November 13, 2023 Go-Live

Common HR System project timeline shows Nov 2023 go-live

  • Configuration Build (Pass 4A) - Feb 14 to April 28, 2023
    • Security role analysis and configuration; system setup 
  • Campus Testing (Pass 5B) - June 1 to July 28, 2023
    • Project Team members system test in a non-production database
  • Final System Validation (Pass 6C) - Sept 5 to Oct 20, 2023
  • Go-Live/Move to Production - November 2023

What is the difference between CHRS and CHRS Recruiting?

describing the difference between CHRS and CHRS Recruiting

Communications